Between December 11th and 17th; the roof, plumbing and AC work was finished and the electrical wiring was installed. The exterior of the house will have 2 carraige lights and 2 uplights to highligh the chopped limestone areas of the exterior. Additionally, there are 4 can lights, 2 ceiling fan blocks, and 2 spotlights on the exterior of the house, the porch and the patio. The intetior of the house has 38 can lights, 3 ceiling fans with lights, 3 hanging light fixtures, 5 triple bathroom light clusters, 3 sconces, 2 4’ flourescent garage lights, 15 other light fixtures (3 blocked for ceiling fans). There are also 9 data, cable combo drops and 3 additional data drops. All this electrical wiring results in 2 breaker panels being installed in the garage.